Building Department
Building Permit
Requirements
PERMITS
 |
A building permit shall be obtained before construction
begins. |
 |
Constructing, altering, or adding to a structure or
moving a structure from one location to another requires a building
permit. |
 |
Manufactured (modular, mobile) structures require a
permit for the tie-downs. |
 |
Plans for the construction of foundations and/or
basements on which the manufactured structure sets are required.
|
 |
Structures shall be located within setback requirements
and shall not be located on utility, road, or irrigation easements or
rights-of-way. |
 |
Fences six feet (6') and under are not required to have
a building permit, however, the owner is advised that, if it becomes
necessary to remove the fence, it will be done at the owner's expense.
|
 |
Fences shall not interfere with visibility at
intersections.
|
INFORMATION ON PLANS AND SPECIFICATIONS
 |
Plans and specifications are required PRIOR to issuance
of a building permit. |
 |
Plans (drawings) shall be drawn to a professional
standard, to scale, upon substantial paper, and be of sufficient
clarity to indicate the nature and extent of the work proposed.
|
 |
Plans shall include a plot plan showing the location of
all existing and proposed structures on the parcel and their distance
from the property lines and road rights-of-way. |
 |
Plans shall contain floor plans that include
foundations and/or basements, all floor levels, lofts, patios,
porches, balconies, carports, garages, and outbuildings. |
 |
Plans shall include exterior structure dimensions and
square footage with separate figures for living space, basement,
carport/deck, garage, etc. (UBC 106). |
Cross-section drawings of building(s)
shall include:
 |
Footings and foundations; |
 |
Spans for floor joists and materials (clearance between
bottom of floor joist, or bottom floors without joists, and the ground
shall be no less than 18 inches; minimum under girders shall be 12
inches); |
 |
Spans for roof trusses or stacked roof--include type of
materials to be used;
Spacing of wall studs and materials used;
Type of finishing materials (interior/exterior). |
 |
Computation, stress diagrams, and other data sufficient to show the
correctness of the plan shall be submitted when required by the
building official. |
NOTE:
 |
Footings
- 24 inches deep (below frost line or back filled) |
 |
Snow
load in recreation area -- 120 lbs. p/s/f/ live load. |
 |
Snow
load for remaining area -- 30 lbs. p/s/f/ live load.
|
Building Inspector:
Myron Adamson
Assistant:
Kacey Hultenius Ext.
254
Phone: 208.587.2130 Extension 510
Address:
Growth and Development
520 East 2nd South
Mountain Home Idaho
83647
Hours: 8:00am 5:00pm
Monday thru Friday
|
|